Japanese money, Indian contractors for Dhaka’s first metro tunnel

India’s Tata Projects said on 12 November that it has won contract package CP06 of Dhaka’s MRT Line-1 as part of a joint venture with Japan’s Nishimatsu Construction and Toda Corporation.

BIONIC READING

In a Nutshell

  • India’s Tata Projects said on 12 November that it has won contract package CP06 of Dhaka’s MRT Line-1 as part of a joint venture with Japan’s Nishimatsu Construction and Toda Corporation.
  • The package covers a 5.182 km underground section running from the northern end of Nadda underground station to Airport station. It includes three underground stations at Khilkhet, Airport Terminal 3 and the Airport, and Tata expects the work to take five years once construction starts.
  • The Nishimatsu-TPL-Toda joint venture won the main line and station contract, worth Tk 115.91 billion.
  • Dhaka Mass Transit Company Limited (DMTCL) signed contracts with Japanese and Indian companies for four MRT Line-1 packages on 5 November, with the road transport secretary attending as chief guest. The chief representative of JICA’s Bangladesh office was a special guest.
  • Larsen & Toubro, another Indian firm, has won design-and-build contracts for two of the line’s system packages.
  • In September, the government approved a 117.64 per cent cost increase for MRT Line-1, raising its total cost to Tk 1.14 trillion.

Context

MRT Line-1 was approved in 2019. About 16.21 km of its 31.24 km would run underground from the airport to Kamalapur, with around 11.36 km elevated between Kuril and Purbachal. The plan at the time was to finish by December 2026 at a cost of Tk 52,561.43 crore, with JICA providing Tk 39,450.32 crore. That deadline has now arrived, and tunnelling has not started. The revised plan was approved at a meeting chaired by Prime Minister Tarique Rahman. Dhaka’s only working metro line, MRT Line-6, runs entirely above ground. 

Why It Matters

With the main tunnelling contracts signed, the project is moving from planning to construction. That shift comes after the cost has more than doubled and the original completion date has passed. A late start has its own cost. At the September approval, an official warned that JICA would change the interest rate on its loans after September if work was not completed quickly. Bangladesh has never built tunnels under a crowded city, so it will be relying on foreign contractors for the engineering skill. The list of who won those contracts also stands out. Japanese money funds the line, and Indian firms now hold both a civil works package and the systems work. A Chinese-led joint venture, CREC-MIL-MBEC, is building elevated sections of Line-5. Contractors from Japan, India and China are all working on Dhaka’s metro network at the same time. 

What We Think

The five-year timeline only begins once work starts. That makes the actual start date, and how long the city takes to clear land and move underground utilities, the numbers to watch. Cost is the harder question. Back in 2019, reporting found Dhaka’s metro construction cost per kilometre was up to six times higher than India’s. The new contracts give a fresh chance to test that comparison package by package. The loans are in yen, and the debt grows with every delay. As a result, contract supervision carries as much financial weight as the engineering. Having contractors from several countries reduces dependence on any one of them, but it also leaves DMTCL with more joint ventures to coordinate.  

░▒▓█▓▒░